From Atlantic City Electric – Bike Path Closure-Final Phase of our Reliability Project around Rio Grande Substation
 
Our contractor, Riggs Matting, is starting the matting work this week at the bike path around our Rio Grande substation area for environmental reasons for the entire length of our reliability project for both overhead and underground portions of the job. This work scope will be completed by Riggs Distler from around the Rio Grande Substation north of Satt Blvd. (approximately 3,500 feet north of Satt Blvd.)
 
Weather permitting and any major emergencies, the overhead and underground portion will require the closing the bike path entire length of project until approximately the end of November.
 
Any changes of this schedule will be posted.