The Phase One priority sewer repairs based on the Red Zone inspection process in Middle Township will commence on Monday September 28th at this time. Motorists should try and avoid these areas if possible or find alternate routes.  Thank you for your understanding.

The schedule of repairs is as follows (subject to change as needed):

  • Monday Sept 28th – West Pacific Ave – between Front St & South Boyd Street
  •                                     Highland Ave – Stone Harbor Blvd & Ormond Road
  • Tuesday Sept 29th – Hand Ave – Between Reading Ave & Dias Creek
  •                                     Hand Ave – Between Hamman Ave & Dias Creek
  • Wednesday Sept 30th – Stone Harbor Blvd at Fairmount Road – Shoulder Closing
  • Thursday Oct 1st  – Mechanic Street Between Hamman Ave & Dias Creek